Boeing ahead of schedule

By Warren Wise
The Post and Courier
Friday, June 4, 2010

Boeing Co. is slightly ahead of schedule on construction of its $750 million assembly plant in North Charleston, where it is building a second production line of its hot-selling 787 jet.

The 1.2 million-square-foot factory is expected to open on time, in July 2011, said Marco Cavazzoni, Boeing's vice president and general manager of final assembly and delivery at the company's North Charleston site.

Speaking at the annual meeting of the Charleston Metro Chamber of Commerce on Thursday, Cavazzoni said a realignment of South Aviation Avenue near the plant site is set to begin in September. The so-called topping out of the steel frame should be completed by October, and the shell of the new building likely will be finished in February, he said.

The first delivery of a completed 787 Dreamliner is set for the first quarter of 2012.

"The first delivery will be a really, really, really big party," Cavazzoni said. "We will shape the perception of South Carolina as an aerospace center."

The new assembly plant will open with 1,000 workers and eventually employ at least 3,800.

Boeing has received 866 orders for the 787 Dreamliner, Cavazzoni said.